Industry resources

SSPI in British Columbia

The law says 1 June 2003. The regulator later pointed to 15 February 2007. The whole story on one timeline, with every document linked.

Counterweight Dispatch Reference

When the test is enforced in BC, how the fits inside it, and where every date on the public record comes from.

Two marks to know: explains a term right here. A pill-shaped link, like Safety Standards Act, opens a source document in a new tab, scrolled to the key passage and highlighted, in most modern browsers. A few destinations (PDFs and Technical Safety BC’s site) can’t be auto-highlighted, so those links say where to look instead.

The 10-second answer

The question this whole page answers: when did the SSPI requirement, and its loaded-gap limit, become law in BC?

✓

1 June 2003: the answer the law gives, and the date to follow. BC adopted B44-00 that day with Canada’s own exceptions deleted, which put the SSPI and the 5 mm loaded gap into force for new escalators. It had been allowed since 1 February 2003. A year later, on 1 April 2004, Update No. 1 lowered the index allowed with a skirt deflector from 0.4 to 0.25.

!

15 February 2007: a complication worth knowing about. Technical Safety BC later wrote that SSPI testing began with the code edition that took force in BC on this date. That muddies the water a little, but it does not outrank the law: the Safety Standards Act says that where a regulation and regulator guidance conflict, the regulation prevails, and the directive that named this date has since been rescinded. Plan around June 2003; just be aware an inspector may mention 2007.

✓

Every escalator in service gets the SSPI test. A unit’s age changes the numbers it must achieve, never whether it is tested.

The timeline

How the requirement reached BC

Published by ASME/CSA, not law in BC Became BC law The recommended start date
2001≈ Jan
Published, not BC law

SSPI and the loaded gap are invented

ASME publishes A17.1d-2000, an that creates both the index and the 5 mm-under-load gap limit. No legal force in BC yet.

ASME A17.1 (sold, not free)
2001Apr
Published, not BC law

CSA publishes B44-00

The base book of the Canadian elevator and escalator code, CSA B44-00. It prints the American SSPI and loaded-gap rules, then sets them aside for Canada: a Canadian clause (c6.1.3.3.5) swaps the 5 mm loaded gap for a static limit of 4 mm a side and 7 mm in total, and notes say the SSPI and its field test are “not part of the B44 Code.” BC adopts this book almost two years later.

CSA B44-00, pp. 315–316 (sold, not free)
2002Sep
Published, not BC law

CSA publishes B44-00 Update No. 1

The that brings the SSPI and the loaded gap into the Canadian code for every province, and lowers the index allowed with a skirt deflector from 0.4 to 0.25. BC adopts it 19 months later, but switches the SSPI and loaded gap on before then.

CSA Update No. 1 (sold, not free)
20031 Feb
BC law

B44-00 arrives in BC, with the SSPI and loaded gap switched on

Allowed to the outgoing code. BC adopts the base book with no updates, but deletes Canada’s own exceptions by name: the static-gap clause c6.1.3.3.5, and the notes that set aside the SSPI, skirt deflectors and both field tests. With those gone, the book’s own rules apply: the SSPI and the 5 mm loaded gap. The regulation keeps both field tests for acceptance and special inspections, and strikes the words that limited the loaded-gap test to newer escalators.

20031 Jun
★ The start date: it is the law

Old code withdrawn: the SSPI and loaded gap are now required

The outgoing CAN/CSA-B44-94 is withdrawn and the BC-modified B44-00 stands alone. From this day a new BC escalator has to meet the 5 mm loaded gap and an SSPI of 0.15 or less (0.4 with a skirt deflector).

20041 Apr
BC law

BC adopts Update No. 1: a tighter deflector limit

A new regulation adopts B44-00 with Updates 1–3. Update No. 1 lowers the SSPI allowed with a skirt deflector from 0.4 to 0.25. It also brings the SSPI and loaded gap into the Canadian code for every province, so BC’s 2003 deletions aren’t needed any more, and the new regulation drops them.

2004
Published, not BC law

CSA publishes B44-04

The next full edition of the Canadian code, loaded-gap limit built in. BC stays on its modified B44-00 for now. This edition does not become BC law for almost three years.

CSA B44-04 (sold, not free)
200715 Feb
The complication: what the regulator said

BC adopts B44-04, the edition the regulator points to

later wrote that SSPI testing entered the code with the 2004 edition, in force in BC from this date. That statement muddies the water a little, but a directive is guidance, not law: the Safety Standards Act settles any conflict in the regulation’s favour, and this directive has since been rescinded. Worth knowing because an inspector may still cite it; not the date to plan around.

2007
Published, not BC law

One book for two countries: A17.1-2007 / B44-07

ASME and CSA merge their two codes into a single book, ASME A17.1-2007/CSA B44-07. Every edition since covers both countries. BC adopts it more than three years later.

A17.1-2007/B44-07 (sold, not free)
201025 Nov
BC law

B44-07 adopted, then a nine-and-a-half-year hold

BC skips the 2010 and 2013 editions entirely and runs on B44-07 until 2020, provable from the regulation’s .

2010
Published, never BC law

B44-10, the first edition BC skips

A new edition of the harmonized book. BC never adopts this one. The province stays on B44-07.

A17.1-2010/B44-10 (sold, not free)
201321 Oct
Published, never BC law

B44-13, skipped too

The second edition in a row BC never adopts. The province is still running on B44-07, now six years old.

A17.1-2013/B44-13 (sold, not free)
201417 Feb
Regulator guidance

The SSPI enforcement push: Directive D-ED 2014-01

BC’s only SSPI-specific document ever issued. It required the test at acceptance (new units and major alterations) and after a step-to-skirt entrapment on any unit installed under B44-04 or later. Units installed under an earlier edition also had to come out of service after an entrapment, but the contractor only had to verify “compliance to the applicable Code”. No index test was called for on those. Contractors got 60 days to buy the equipment. A , not a regulation.

201630 Nov
Published, not BC law yet

B44-16 is published

The edition BC runs on today, though it sits on the shelf for another three and a half years before BC adopts it.

A17.1-2016/B44-16 (sold, not free)
2019
Published, never BC law

B44:19 is out, and BC still hasn’t adopted B44-16

The next edition arrives before BC adopts the previous one. BC never adopts B44:19. It goes straight from B44-07 to B44-16 the following spring.

A17.1-2019/B44:19 (sold, not free)
202030 Apr
BC law, current

B44-16, today’s code

The edition in force in BC now. The 2014 directive was as a result. The code moved on, not the requirement.

2022
Published, not BC law

B44:22 is published

Another edition of the harmonized book. BC stays on B44-16.

A17.1-2022/B44:22 (sold, not free)
202630 Jan
Published, not BC law

B44:25, the newest edition

The most recent book of the code itself, named for its 2025 cycle, published 30 January 2026. BC law still points at B44-16, three editions back, so B44-16 remains the code that governs BC work today.

The part nobody explains

One test, two rulebooks

“Every escalator needs the SSPI test, but not every escalator needs the loaded-gap limit. How can that be? Aren’t they the same test?”

They are. The SSPI and the loaded gap are inseparable when the instrument is on the step: one pass always measures both. It’s the unit’s date that decides what to do with the results. Here is the whole trick:

The instrument pass

With the escalator running, a plastic test block is pressed sideways from the step against the skirt panel at a set force of 110 N (about 25 lbf) and dragged along. The skirt must not be cleaned or lubricated first: the test wants the panel as passengers get it.

↓one pass produces two numbers

μ: friction

How much the block drags on the skirt: the .

Lg: the loaded gap

How wide the step-to-skirt gap is while that same 110 N is pushing. This is the loaded gap, measured during the pass, not separately.

↓combined by the code’s formula

The index

Both numbers feed one formula, and the result is the SSPI:

SSPI = ey / (ey + 1),  where  y = −3.77 + 2.37 μ + 0.37 Lg

Notice Lg is inside the formula, and the same formula appears in the code for existing installations. The loaded gap gets measured on every unit, old or new, every time the index is taken.

↓then the unit’s era decides which limits those numbers face
Every unit

Index limit

The SSPI number must achieve a threshold. Modern units: 0.15, or 0.25 with a . Existing installations: 0.15 / 0.4 with a deflector.

Units installed ≥ 1 Jun 2003 (BC)

+ Loaded-gap limit

The Lg reading also has its own pass/fail line: no more than 5 mm under the 110 N load. This standalone limit is the part that only exists for newer units.

Older units instead

Static clearance

Units installed before June 2003 aren’t held to the 5 mm-under-load line. Their gap rule is their own edition’s limit, checked without the load.

So the answer is: you never separate the tests. You separate the limits. The loaded gap is measured on every unit because it is one of the two numbers inside every SSPI reading. What changes with a unit’s era is whether that gap number also has its own pass/fail limit (in BC, units installed from 1 June 2003 on) or is judged the old way, as a static clearance (everything before). Vintage picks the rulebook, never whether the test happens.
Your unit

Which rules bind a BC escalator

Installed before 1 June 2003

  • SSPI test: yes. Index measured the same way, judged against the existing-installations thresholds (0.15, or 0.4 with a deflector).
  • Loaded-gap 5 mm limit: no. The gap is judged by the static clearance limit of the B44 edition the unit was installed under instead.

Installed 1 June 2003 to 31 March 2004

  • SSPI test: yes. Judged against 0.15, or 0.4 with a deflector, the limits in B44-00 itself.
  • Loaded-gap 5 mm limit: built to it. BC’s version of B44-00 required the loaded gap for these units.
  • One open question: today’s code lists plain B44-00 units at a 4 mm / 7 mm static limit, because its note describes the national book, not BC’s version. For a unit from these ten months, ask Technical Safety BC which it applies. The loaded gap is the rule the unit was built under.

Installed (or altered) 1 April 2004 or later

  • SSPI test: yes. Judged against the modern thresholds (0.15, or 0.25 with a deflector).
  • Loaded-gap 5 mm limit: yes. The Lg reading has its own pass/fail line at 110 N.
  • Alterations count: a major alteration puts a unit under the code in force at the time of the alteration.

The 2014 entrapment rule is history, not a current requirement. Directive D-ED 2014-01 was rescinded after BC adopted B44-16. While it stood, it split escalators at CAN/CSA B44-04, which took force in BC on 15 February 2007. After a step-to-skirt entrapment, a unit installed under B44-04 or later had to be shut down and its step/skirt performance verified in front of a safety officer. A unit installed under an earlier edition was shut down too, but the contractor only had to verify “compliance to the applicable Code”. Directive PDF: part (B), pp. 1–2 Rescission notice

The numbers, by CSA B44 edition
Installed under
SSPI index
Step-to-skirt gap
B44-1960 – B44S3-1982
≤ 0.15
≤ 0.4 with deflector
≤ 4.8 mm each side
≤ 6.4 mm total
B44-1985 – B44S2-1998
BC ran B44-94 + B44S1-97 until 2003
≤ 0.15
≤ 0.4 with deflector
≤ 5 mm each side
≤ 6 mm total
CSA B44-00
BC: 1 Jun 2003 – 31 Mar 2004
≤ 0.15
≤ 0.4 with deflector
≤ 4 mm each side
≤ 7 mm total
BC’s version: ≤ 5 mm loaded gap
B44-00 Update 1 or later
BC: 1 Apr 2004 onward
≤ 0.15
≤ 0.25 with deflector
≤ 5 mm loaded gap
under the 110 N load

These rows are keyed on the CSA B44 edition a unit was installed under, not on its installation year. That is how the code itself sets them out, in the “NOTE (on CSA B44 Requirements)” carried by ASME A17.1-2016/CSA B44-16 against the step/skirt clearance requirement. Check the edition on the unit’s code data plate rather than working back from the year: BC’s adoption dates are documented from 2003 onward (B44-00 mandatory 1 June 2003, Update 1 on 1 April 2004), but its adoption dates for earlier editions are not published. In the first three rows the gap figure is that edition’s static clearance, measured with no sideways load, and the last row uses the loaded gap. The one exception in BC is the B44-00 row: BC deleted the Canadian clause that set the static limit, so its version of B44-00 required the 5 mm loaded gap. The index thresholds are the code’s existing-installations rule (0.15, or 0.4 with a deflector) and the modern rule (0.15, or 0.25).

A note on the American figures. The same code book carries a second, parallel note for ASME A17.1 editions, with different numbers, including a 9.5 mm allowance for units installed under A17.1-1971 through A17.1-1979, and a bucket that folds in ASME A17.3. Those belong to the ASME sequence only. BC has never adopted ASME A17.1 on its own, and has never adopted ASME A17.3. Neither appears in B.C. Reg. 101/2004 or in the former B.C. Reg. 28/90, which ran CAN/CSA-B44-94 with Supplements 1 and 2. So the 9.5 mm figure and A17.3’s flat 4.8 mm have never applied to a BC unit.

Enforcement

How the test is enforced in BC today

  • Routinely: SSPI is part of the recurring periodic test cycle under today’s code (B44-16, requirement 8.6.8.15.19), which BC adopted by regulation.
  • Historically pushed hard: from 2014 to 2020 the directive also demanded it at acceptance and after a step-to-skirt entrapment on any unit built to B44-04 or later, with real teeth (60-day equipment deadline; non-compliant escalators “will not be put into service”).
  • Hierarchy: where guidance and law disagree, the Safety Standards Act (s.30(4)) settles it: the regulation prevails. The directive is rescinded; the regulation-adopted code requirement stands.
  • What BC has never published: an SSPI limit table. Ontario has, and it is the clearest published example of the thing BC leaves unwritten: TSSA Advisory ED-300-21 sets out four bands of pass criteria keyed to the date a unit was registered, and spells out what makes a test chart invalid. It has no force in BC. It shows what a published answer looks like. The only BC-published SSPI figures appear as narrative in one incident investigation (the figures sit under “Investigation conclusions”). For a binding answer on a specific unit, ask Technical Safety BC.
The document shelf

Every source behind this page

B.C. Reg. 29/2003The 2003 adoption of B44-00, with no updates, and the list of Canadian clauses and notes it deleted, in its own words. bclaws.gov.bc.ca
Reg 29/2003, Dec 2003 viewProof BC still ran plain B44-00, no updates, late in 2003. bclaws.gov.bc.ca
B.C. Reg. 101/2004, as enactedUpdate No. 1 arrives: the deflector limit tightens to 0.25, and the 2003 deletions are no longer needed. Effective 1 Apr 2004. bclaws.gov.bc.ca
Reg 101/2004, currentToday’s text: “ASME A17.1-16/CSA B44-16”. bclaws.gov.bc.ca
Reg 101/2004, point in timeAmendment history; proves B44-10 and B44-13 were skipped. bclaws.gov.bc.ca
BC Gazette v50 n04Reg 17/2007: B44-04 adopted, effective 15 Feb 2007. bclaws.gov.bc.ca
Directive D-ED 2014-01BC’s only SSPI document, now rescinded. 2-page PDF. The dates sentence is under “Specific Details” on page 1. web.archive.org
Directive rescission noticeWithdrawn following B44-16 adoption: superseded, not disowned. Look for the “Rescinded” box at the top. technicalsafetybc.ca
Incident II-657117-2018Boot entrapment; the only BC-published SSPI figures found, under “Investigation conclusions.” technicalsafetybc.ca
Technical Safety BCCurrent elevating-devices regulatory landing page. The adoption date sits under “CSA B44 Safety Code.” technicalsafetybc.ca
Safety Standards ActThe governing statute; s.30(4): the regulation prevails. bclaws.gov.bc.ca
TSSA Advisory ED-300-21 (Ontario)Ontario’s published SSPI table, the model of every-era-tested. Four bands keyed to a unit’s registration date. tssa.org
CSA B44-00 (April 2001)The book BC adopted in 2003. Its preface explains the lower-case “c”. Clause c6.1.3.3.5 is on p. 315, and the notes setting aside 6.1.3.3.7, 6.1.3.3.8, 8.11.4.2.19 and 8.11.4.2.20 are on pp. 316 and 568–569. Sold by CSA, not free to read
ASME A17.1 / CSA B44-16, A17.2, A17.3The code books: the limit (6.1.3.3.5), the index (6.1.3.3.9), the test (8.6.8.15.19), the existing-installation thresholds (8.6.8.3, and the NOTE on CSA B44 requirements under the step-to-skirt clearance rule). Sold by ASME/CSA, not free to read
Honesty
  • This is a research summary, not legal advice. Adoption dates and enforcement practice change. For a binding answer about a specific unit, ask Technical Safety BC or your authority having jurisdiction.

Counterweight Dispatch reference series. Compiled from public regulatory records.
Last verified: 26 September 2026. If you are reading this anywhere other than counterweightdispatch.com, check there for the current version.

These materials contain information that has been derived from information originally made available by the Province of British Columbia at: www.bclaws.gov.bc.ca and this information is being used in accordance with the King’s Printer Licence – British Columbia available at: bclaws.gov.bc.ca/standards/Licence.html. They have not, however, been produced in affiliation with, or with the endorsement of, the Province of British Columbia and THESE MATERIALS ARE NOT AN OFFICIAL VERSION.

← Back to Resources

Working to the escalator code on the job?

Escalator Field Command is a maintenance app for escalator mechanics: routes, CAT1 testing, documents and the Escalator Field Guide, on your phone.

Free briefing, every two weeks

The Counterweight newsletter is a free email briefing for people who work on elevators and escalators. Code changes and incidents, with every source linked so you can check it yourself. Unsubscribe anytime.

We send the briefing and nothing else. No sharing your address.